Combined Heat & Power Case Study — Combined Heat and Power Plant

APPLICATION DETAILS:

Design, supply and installation of acoustic enclosures and ventilation systems for gas engine on hospital site

SUPPLY SCOPE:

Site-assembled galvanised steel acoustic enclosure with demountable side wall section. Enclosure installed with 2 no. 500kg lifting beams, tested and certified on site. Ventilation system designed to connect to existing external weather louvres in boiler house. Ventilation system comprised of 2 no. axial flow fans, motorised dampers, inlet filters and louvres along with attenuation and ductwork systems

PRODUCT SELECTION AND PERFORMANCE:

Enclosure and attenuation designed to reduce noise levels to 70dBA at 1m based upon untreated levels of 100-105dBA